Q 1.Consider a workstation that can process 4000 units per hour. It takes 15 minutes to receive an order from the previous station. The container size is 20 units. The factory sets safety stock at 20 percent of demand during lead time. How many kanbans are needed for the workstation? 2.An improvement tool that utilizes cross-functional teams to plan and deliver improvements to specific processes during two- or three-day marathon sessions is called a . 3.Consider a workstation that can process 4 units per minute. It takes 2 hours to receive an order from the previous station. The container size is 10 units. The factory sets safety stock at 20 percent of demand during lead time. How many kanbans are needed for the workstation? 4.Three basic elements work together to complete a JIT system: just-in-time manufacturing, total quality management, and . 5.The central belief of the JIT philosophy is